99.04: Excavation Notification

 

(1)  Notice of an excavation shall be tendered to the Dig Safe Center at least 72 hours, exclusive of Saturdays, Sundays, and legal holidays, but not more than 30 days prior to the commencement of an excavation. Such notice shall include an accurate description of the excavation location and the scope of the work to be performed.

(2)  Notice of an excavation by blasting shall be tendered to the Dig Safe Center at least 72 hours in advance and shall accurately specify the date and location of such blasting. In the case of an unanticipated obstruction requiring blasting, notice shall be given not less than four hours prior to such blasting.

 

Amended by Mass Register Issue 1402, eff. 10/18/2019.