NOTIFICATION OF CONSTRUCTION
FOR
GAS GATHERING LINES TO BE SUBJECTED TO PRESSURE OF 125 PSIG OR MORE
OR
FOR GAS GATHERING LINES TO BE LOCATED IN AN AREA USED FOR COMMERCIAL FARM PURPOSES
COMPANY _________________________ DATE ______________________________
DESCRIPTION OF PROJECT _______________________________________________
_________________________________________________________________________
_________________________________________________________________________
_________________________________________________________________________
LOCATION OF PROJECT (file a copy of the map filed with the Article VII application)
_________________________________________________________________________
_________________________________________________________________________
ESTIMATED STARTING DATE _____________________________________________
ESTIMATED COMPLETION DATE __________________________________________
PERSON TO BE CONTACTED REGARDING PROJECT _________________________
ADDRESS ________________________________________________________________
_____________________________________ TELEPHONE NO._____________________
MAXIMUM ALLOWABLE OPERATING PRESSURE ____________________________
LOCATION CLASS* ________________________________________________________
PIPE & COATING DESCRIPTION
a. NOMINAL DIAMETER _____________________________
b. NOMINAL WALL THICKNESS _______________________________
c. PIPE SPECIFICATION _______________________________
d. GRADE _________________________________
e. COATING TYPE ________________________________
f. METHOD OF APPLICATION _______________________________
g. LONGITUDINAL JOINT TYPE ________________________________________
TEST DATA:
a. TEST MEDIUM ____________________________
b. DURATION _____________________________
c. TEST PRESSURE ______________________________
NAMES AND MAILING ADDRESSES OF AFFECTED FARMLAND OPERATORS:
Name |
Mailing Address |
|
|
|
|
|
|
|
|
* If the line is to be constructed within 150 feet of an existing structure used for a residence or place of business that portion of the line must be constructed to transmission line standards. Under these circumstances, contact the Albany Office of the Gas Division prior to construction: (518) 474-5453.